The project is located in the Second District, on a separating street between two neighborhoods. The neighborhoods are distinguished by their readiness in terms of infrastructure, road paving, lighting poles, etc. – The Second District is also distinguished by its proximity to the northern 90th Street and the club area, in addition to the most prestigious urban communities such as Palm Hills and Mountain View. The width of the street is 30 meters. In addition to its proximity to the services area and green areas.
Project features
On a two-way main street
On separator street
Steps from North 90th Street
Minutes from the club area
🏡 Plot 31M – Second District – Beit Al Watan “Month of August”
- The project has been completed
🏡 Plot 31M – Second District – Beit Al Watan “Month of May”
- The installation of front lights and fence lights is being completed and preparations are being made for final deliveries.
🏡 Plot 31M – Second District – Beit Al Watan “Month of April”
The installation of front lights and fence lights is being completed and preparations are being made for final deliveries.
🏡 Plot 31M – Second District – Beit Al Watan “February”
- In the final finishing stage.
🏡 Plot 31M – Second District – Beit Al Watan “January”
- Waiting for the final finishing of the doors, air conditioners and electrical supplies
🏡 Plot 31M – Second District – Beit Al Watan “December”
- The external facades and marble entrances are being completed
🏡 Plot 31M – Second District – Beit Al Watan “Month of November”
- Work is underway on the exterior facades, interior finishes, and fences
🏡 Plot 31M – Second District – Beit Al Watan “October”
- Starting the exterior facade finishing works, gypsum and GRC works, and roof insulation
🏡 Plot 31M – Second District – Beit Al Watan “Month of September”
- Completion of building and plastering works for the front and side facades
🏡 Plot 31M – Second District – Beit Al Watan “Month of August”
Interior and exterior plastering, electrical and plumbing works
🏡 Plot 31M – Second District – Beit Al Watan “July”
- Conch works and buildings
🏡 Plot 31M – Second District – Beit Al Watan “June”
- The works of the third floor buildings and the concourse are complete
🏡 Plot 31M – Second District – Beit Al Watan “Month of May”
- Casting of the roof roof and columns and commissioning in the basement and ground floor buildings
🏡 Plot 31M – Second District – Beit Al Watan “April”
- The columns are being poured for the second floor, and some basement work is underway
🏡 Plot 31M – Second District – Beit Al Watan “Month of March”
- Starting carpentry and blacksmithing work for the project.
Start blacksmithing the ceiling of the first floor.
Source text
80 / 5,000
Translation results
Translation result
- 🏡 Plot 31M – Second District – Beit Al Watan “January” Blacksmithing and casting of the raised basement ceiling
🏡 قطعة 31M – الحي الثاني – بيت الوطن “شهر يناير”
- حدادة وصب سقف البدروم المرتفع
🏡 Plot 31M – Second District – Beit Al Watan “December”
- The walker was poured and the bases and smalts of the columns were insulated in preparation for building the fences, resuming the concrete, then insulation, and building the fence.
🏡 Plot 31M – Second District – Beit Al Watan “Month of November”
- The reinforced bases and the columns and walls were poured
🏡 Plot 31 – Second District – Beit Al Watan “October”
- Starting excavation work
Show more
El Shorouk | Eighth District | Project 249
Under Construction Load more →
Fifth settlement | Bait Al waten | third District | Project F94
Under Construction Load more →
Humberto
2024-11-14 10:22:35молодость работа дом тест на определение профессии после 9 класса для девушек онлайн подработка уборщиком спб курган подработка уборщица вечерняя Feel free to visit my web-site - как заработать деньги через интернет без вложений